|
* |
The Concept: Product identification
and establishment of development
criteria |
|
* |
Identify all sources of seed capital |
|
* |
Assemble Internal Team: Site
Acquisition, financial analysis,
marketing, negotiations. |
|
* |
Market Area Identification |
|
* |
Location Possibilities |
|
* |
Feasibility Studies |
|
* |
Market Analysis & Study |
|
*
|
Site Analysis: Preliminary
environmental study, suitability for
desired purpose; identify potential
obstacles/opposition |
|
*
|
Preliminary Pro Forma: use of market
knowledge to estimate cost,
potential income and expenses,
possible operating profit and
project final sales value;
estimating value added by
development process; ascertaining
available financing |
|
* |
Risk/Reward Analysis |
|
* |
Land Acquisition: optioning the
land, securing control |
|
* |
Obtain Environmental Phase 1 Report,
Soil Borings Analysis On-Site |
|
* |
Preliminary Contacts with Possible
Debt and Equity Sources |
|
*
|
Assemble External Team: Architect,
engineer, land planner, landscape
architect, surveyor, legal; lining
up possible general contractors;
signing contracts with major
professionals; detailing levels of
responsibility; clarifying areas of
involvement |
|
* |
Design Process: Site, structures,
and specifications |
|
* |
Begin Formulating Marketing/Leasing
Plan |
|
* |
Prequalify, evaluate and select
Property Management Team, Sign
Contingent Contract |
|
*
|
Estimating and Preliminary Bidding
Process; Ongoing interaction with
potential Construction Managers or
Contractors re cost estimates,
design suggestions, value analysis,
and specifications |
|
* |
Regulatory Approval Process: Zoning
vs. site plan approval |
|
* |
Obtain Final Construction Documents
and Site Plans |
|
* |
Release Final Construction Documents
to CM & GC Potentials |
|
* |
Raise Equity Capital, Finalize Deal
Structure and Form of Ownership
Entity |
|
*
|
Debt Capital; Construction Loan:
Send out project loan packages,
receive terms sheets, submit loan
application, expedite required
third-party reports, obtain
commitment letter. |
|
* |
Receive preliminary bids, Value
Engineering, and Final Bids |
|
* |
Negotiate CM/GC Contract and
Establish Construction Schedule |
|
*
|
Conduct Risk/Reward - BE Analysis:
Review Pro Forma and assumptions
therein, assess available debt and
equity capital; CM/GC Contract; Make
go/no go decision |
|
* |
Sign - Execute Construction Contract |
|
* |
Obtain Building Permit |
|
*
|
Close on Land Option, Close
Construction Loan, File Notice of
Commencement, Give Notice to Proceed
to CM/GC |
|
* |
Ground Breaking |
|
* |
Begin Oversight of Construction
Process, Exercise Quality Control |
|
* |
Manage Marketing/Leasing Program,
Fine-Tune Interior Design Issues |
|
* |
Field Visits and Progress Reports,
Approve Construction Drawings and
Change Orders |
|
* |
Punch Lists Management and Close Out |
|
* |
Certificate of Occupancy |
|
* |
Substantial Completion |
|
* |
As-Built Survey |
|
* |
Lease Up |
|
* |
Occupancy/Grand Opening |
|
* |
Stabilization |
|
* |
Convert Construction Loan to
Short-Term Permanent Loan |
|
* |
Depending on Exit Strategy (Flip vs.
Hold), either |
|
* |
Begin
or Intensify Marketing for Sale, or |
|
* |
Circulate
Updated Permanent Loan Packages |
|
* |
Start or Intensify Search for New
Development Opportunity |
 |
 |